Endeavour Mining Corporation: Endeavour Provides Houndé Project Update; Construction Progressing On-Time and On-Budget

EndeavourProvides Houndé Project Update;
Construction Progressing On-Time and On-Budget
View News Release in PDF Format
http://hugin.info/171882/R/2040076/760947.pdf
George Town, September 6, 2016 -
Endeavour Mining Corporation (TSX:EDV)(OTCQX:EDVMF) (the "Company") is pleased to announce that excellent progress is being made at its Houndé Gold Project in Burkina Faso. Construction is progressing on-time and on-budget, with the first gold pour expected during the fourth quarter of 2017.Jeremy Langford, EVP Construction Services Group of Endeavour, stated:

"We are very pleased to have successfully achieved our first set of key
project milestones safely, ahead of schedule and on-budget, despite the
wet-season being upon us. Our employment statistics are extremely pleasing
with over 96% of our 1,058 project staff and contractors being Burkinabe
Nationals. I am proud that this project will deliver significant economic
benefits to the local area and the whole of Burkina Faso, in addition to
becoming Endeavour's flagship operating mine."

Key milestones achieved to date include:

* Procurement is approximately 45% complete, with total capital commitments
amounting to $150 million.
* CIL ring beam concrete pour achieved early-August, two weeks ahead of
schedule. As of September 6th, all six ring beams have been completed.

* Mining fleet equipment financing agreement signed with Komatsu Ltd., with
deliveries already on-site, machinery commissioned and operational.

* Water harvest dam construction completed, with water already being pumped
to the water storage dam, two months ahead of schedule.

* Construction of the 300-person permanent accommodation village is 30%
complete and on-schedule for completion during Q1-2017.

* Crusher civil earthworks commenced late August.

* Following the signing of the power offtake agreement with Sonabel, the
national electricity provider, procurement has been completed for the 38km
91kv overhead power line with construction scheduled to start in October
2016.
* Detailed engineering of the processing facility is progressing well and on
schedule to be completed mid-November 2016.
* 1,058 personnel including contractors are currently employed on-site, of
which over 96% are Burkinabe, exceeding Endeavour's objectives.
* Strong safety record with over 400,000 man-hours worked without a Lost Time
Injury (LTI) or Medical Treatment Injury (MTI).
* The land compensation process has been successfully completed and
resettlement is underway, with all approvals in place.

About the Houndé Project
Once in production, Endeavour's 90%-owned Houndé Project will become the
Company's flagship low-cost mine, ranking amongst West Africa's top tier cash
generating mines, with an average annual production of 190,000 ounces at an
All-In Sustaining Cost ("AISC") of US$709/oz over an initial 10-year mine
life based on reserves. In its first 4 years, the average annual production
is expected to be 235,000 ounces at an AISC of US$610/oz[1].

The project is an open pit mine with a 3.0Mtpa gravity circuit /
Carbon-In-Leach plant. The initial capital cost is estimated at $328 million,
inclusive of $46 million for the owner-mining fleet. Construction began in
April 2016 and is progressing on-time and on-budget with the first gold pour
expected during the fourth quarter of 2017.

Endeavour will employ up to 1,800 people during Houndé's construction phase
and 470 once the project reaches commercial production, with an objective of
employing 90% Burkinabe nationals and a focus on increasing female employment
in the region.

[1] As announced in Endeavour's April 11, 2016, news release entitled
"Endeavour starts construction of its Houndé Project, its next low-cost gold
mine" available on the Company's website and on Sedar.

About Endeavour Mining Corporation
Endeavour Mining is a TSX-listed intermediate gold producer, focused on
developing a portfolio of high quality mines in the prolific West-African
region, where it has established a solid operational and construction track
record.

Endeavour is ideally positioned as the major pure West-African multi-operation
gold mining company, operating 5 mines in Côte d'Ivoire (Agbaou and Ity),
Burkina Faso (Karma), Mali (Tabakoto), and Ghana (Nzema). In 2016, it expects
to produce between 575koz and 610koz at an AISC of US$870 to US$920/oz.
Endeavour is currently building its Houndé project in Burkina Faso, which is
expected to commence production in Q4-2017 and to become its flagship
low-cost mine with an average annual production of 190koz at an AISC of
US$709/oz over an initial 10-year mine life based on reserves. The
development of the Houndé project is expected to lift Endeavour's group
production +900kozpa and decrease its average AISC to circa $800/oz by 2018,
while exploration aims to extend all mine lives to +10 years.

Contact Information

---------------------------------------------------------------------
| Martino De Ciccio DFH Public Affairs in Toronto |
| |
| |
|VP - Strategy&Investor Relations John Vincic |
|+33 (0)1 70 38 36 95 (416) 206-0118 x.224 |
|mdeciccio@endeavourmining.com jvincic@dfhpublicaffairs.com |
| |
| |
| |
| |
| Brunswick Group LLP in London |
|Vincent Benoit |
| |
| Carole Cable, Partner |
|EVP - Strategy&Business Development +44 7974 982 458 |
|+33 (0)1 70 38 36 96 ccable@brunswickgroup.com |
|vbenoit@endeavourmining.com |
---------------------------------------------------------------------
Qualified Persons

Adriaan "Attie" Roux
, Pr.Sci.Nat, Endeavour's Chief Operating Officer, is a Qualified Person under
NI 43-101, and has reviewed and approved the operational analysis, operating
and capital estimates, and other technical information in this news release.

Endeavour Mining | Executive Office | Bureau 76, 7 Boulevard des Moulins,
Monaco 98000

This news release contains "forward-looking statements" including but not
limited to, statements with respect to Endeavour's plans and operating
performance, the estimation of mineral reserves and resources, the timing and
amount of estimated future production, costs of future production, future
capital expenditures, and the success of exploration activities. Generally,
these forward-looking statements can be identified by the use of
forward-looking terminology such as "expects", "expected", "budgeted",
"forecasts", and "anticipates". Forward-looking statements, while based on
management's best estimates and assumptions, are subject to risks and
uncertainties that may cause actual results to be materially different from
those expressed or implied by such forward-looking statements. Accordingly,
readers should not place undue reliance on forward-looking statements. Please
refer to Endeavour's most recent Annual Information Form filed under its
profile at www.sedar.com for further information respecting the risks
affecting Endeavour and its business.

Komatsu fleet arrivals
http://hugin.info/171882/R/2040076/760955.png
Crusher civil earthworks
http://hugin.info/171882/R/2040076/760958.png
View News Release in PDF Format
http://hugin.info/171882/R/2040076/760947.pdf
Resettlement site
http://hugin.info/171882/R/2040076/760957.png
Water harvest dam
http://hugin.info/171882/R/2040076/760956.png
CIL ring beam
http://hugin.info/171882/R/2040076/760954.png

---------------------------------------

This announcement is distributed by Nasdaq Corporate Solutions on behalf of Nasdaq Corporate Solutions clients.
The issuer of this announcement warrants that they are solely responsible for the content, accuracy and originality of the information contained therein.
Source: Endeavour Mining Corporation via Globenewswire

Författare Hugin

Tala om vad ni tycker

Tala om vad ni tycker

Ni är just nu inne på en betaversion av nya aktiespararna. Lämna gärna feedback på vad ni tycker i formuläret nedan.